Example
|
|||
Number of Trucks using Reclaimer:
|
20
|
Numbers of Trucks:
|
____________
|
Estimated Waste per Day per Truck:
|
x 1.5 cubic yards
|
Estimated Waste per Truck:
|
____________
|
Total Waster per Day:
|
30 cubic yards
|
Waster per Day
|
____________
|
Number of Operating Days per Year:
|
x 260
|
Operating Days:
|
____________
|
Total Waste per Year:
|
7,800 cubic yards
|
Total Waste per Year:
|
____________
|
Cost of Aggregate per cubic yard:
|
$14.00
|
Cost of Aggregate per cubic yard
|
____________
|
Value of Aggregate per cubic yard left on the Ground:
|
$109,200.00
|
Value of Aggregate per cubic yard left on the Ground:
|
____________
|
98% Recovery Factor:
|
.98
|
98% Recovery Factor:
|
____________
|
TOTAL VALUE
of RECOVERED AGGREGATE per Year!
|
$107,016.00
|
TOTAL VALUE
of RECOVERED AGGREGATE per Year!
|
____________
|
OTHER THINGS TO CONSIDER
|
Every Ton of Aggregate You Re-Use is a Ton You don't have to Haul in or Haul out as Waste
|